Answer

The Australian Energy Market Operator (AEMO) has identified several new lines that will need to be built over the next 20 years in order to meet our energy needs. 

The below infographic from AEMO details where the transmission lines will need to be, roughly. More detail on AEMO's plan for the future of our National Electricity Market can be found here

Some of these lines are already well into their planning stages, including:

Transmission Project
Purpose
Built by
Western Victoria Transmission Line

connect the West & South-West Coast Renewable Energy Zones (REZs) with the rest of Victoria

AusNet Services
Project Energy Connect

run from Wagga Wagga in New South Wales across to Robertstown in South Australia, connecting 4 Renewable Energy Zones to the grid in the process

Transgrid and Electranet
Marinus Link

strengthen the connection from Tasmania to the mainland & enable Tasmania to reach their target of 200% renewable energy by 2040

TasNetworks
Central West Orana REZ Transmission link

connect the Central-West Orana region, hosting the pioneering REZ in NSW, to the grid

TransGrid